4 week sprint - different types of tasks

Rationale

Two weeks is quite short (minimal in Agile - acceptable if you have e.g. 6 people working in same room 8 hours per day - we have people all over europe with 0.5-8 hours per day and other projects (context-switching)) + we need more time for design/requirements engineering/testing (now ad-hoc - in Agile → between sprints planning + design + requirements engineering) - otherwise we get design debt. Everyone involved in design → no fixing things afterwards which could have be done good in the first place.

New Sprint Model

Warm-up

Implementation

Finish



Planning:

Week 2 (starting Jan 9) - new years resolution sprint (design(!), requirements engineering, when are deliverables? (+what is needed? Development dependencies! Design!), some prototyping perhaps (what is needed to go to react-semantic UI?).

Week 3 + 4 - intermediate/hybrid sprint (Fix almost-finished features + create automated tests + unit tests + continue design work from new years resolution sprint)

February 1st → deploy/update stable

Februari 3th →  is monthly telco

Week 5-8 - new 4 week sprint model (see above)


Abi James Benjamin Wulff Klaas Andries de Graaf